FREDERICK COUNTY PUBLIC SCHOOLS

HAYWARD COMPLEX

PURCHASING DEPARTMENT

33 THOMAS JOHNSON DRIVE

FREDERICK, MARYLAND  21702

 

 

A.           GENERAL CONDITIONS AND INSTRUCTIONS FOR SMALL CONSTRUCTION, MAINTENANCE AND MISCELLANEOUS SERVICE CONTRACTS

 

1.            PRE-BID MEETING

If warranted, a Pre-Bid Meeting will be held at the date and time indicated on the cover page of this solicitation package.  Unless noted otherwise, the meeting will be held in the Conference Room of the Purchasing Department, located at 33 Thomas Johnson Drive, Frederick, Maryland  21702.

 

Attendance at the Pre-Bid Meeting is Not Mandatory in order for your bid to be considered for an award, yet all vendors are strongly encouraged to attend.

 

The agenda for this Pre-Bid Meeting will include the following:  introduction of staff;  description of scope of work;  timeline/scheduling;  budget priorities/concerns;  and procurement responsibilities.

 

Due to possible changes and/or additions to the specification, bid proposals should not be mailed until after the pre-bid meeting.  All changes will be processed through addenda to this solicitation package.

 

2.            TIME FOR RECEIVING BIDS

Bids received prior to the time of opening will be securely kept unopened.  The representative of the Superintendent, whose duty it is to open bids, will decide when the specified time has arrived.  No bid received thereafter will be considered.  The Superintendent or his/her representative will not be responsible for the premature opening of bids received, not properly addressed or identified.  Any bid may be withdrawn before the scheduled time for opening bids.  After a bid has been opened, it may not be withdrawn.

 

Unless specifically authorized, facsimile bids will not be considered.  Modifications by facsimile of bids already submitted will be considered if received prior to the time set for opening.  No bids will be accepted via telephone.

 

Proposals received after the designated date and/or time will not be accepted, regardless of when they were mailed or given to a delivery carrier.

 

In the event of inclement weather on the date when bids are scheduled to be opened and the Frederick County Public Schools Administrative Offices are closed, bids will be opened on the next business day at the same time as previously scheduled.  Bids will be accepted until the scheduled time of opening on the next business day.  (Often when schools are closed due to inclement weather, administrative offices remain open.  When in doubt, call the Purchasing Department.)

 

3.            RECEIPT AND OPENING OF BIDS

Sealed proposals will be opened in the Purchasing Department of the Frederick County Public Schools, 33 THOMAS JOHNSON DRIVE, FREDERICK, MARYLAND, on the day and hour stated herein.

 

All proposals must be submitted properly executed and securely sealed.  The envelope must be prominently marked with the name of the person, firm or corporation making such proposal, the date of its presentation, and BID/QUOTE NAME AND NUMBER,  to the ATTENTION OF THE PURCHASING OFFICER.  If not bidding, NO BID must be indicated also on the outside of the envelope.

 

4.            PREPARATION OF BID/SIGNATURE

Bids must be prepared on the enclosed proposal form(s) and in accordance with the specifications herein.

 

Each bid must show the full business address and telephone number of the bidder and be signed by the person or persons legally authorized to sign contracts.  All correspondence concerning the bid and contract, including notice of award, copy of contract, and purchase order will be mailed or delivered to the address shown on the bid in the absence of written instructions from the bidder to the contrary.  Bids by partnerships must be signed with the partnership name, followed by the signature and designation of the person having authorized to sign.  Bids by corporations must be signed with the name of the corporation, followed by the signature and designation of the person having authority to sign.  When requested, satisfactory evidence of authority of the person signing will be furnished.  Anyone signing the bid as an agent shall file satisfactory evidence of his/her authority to do so, if requested.

 

Failure to properly sign the bid document will result in rejection of the bid.

 

5.            ERRORS IN BIDS/INTERPRETATION

Bidders or their authorized representatives are expected to fully inform themselves as to the conditions and requirements of the specifications before submitting bids.  Failure to do so will be at the bidder's own risk.

 

Should any bidder be in doubt as to the meaning of the specifications, or should he/she find any discrepancy or omission, he/she shall notify the Purchasing Officer of the Board of Education of Frederick County.  All bidders will then be notified, in writing, of clarification or additional information by means of addenda.

 

Neither law nor regulations make allowance for errors either of omission or commission on the part of the bidders.  In case of error in multiplication of unit price when arriving at total price per line item, the unit price shall govern.  If there is a discrepancy between the price written in numbers and the price written in words, the words will govern.

 

If an error has been made by the bidder, the bidder may request in writing, to have his/her bid withdrawn.  Approval of a bidder's request is not automatic and may be given only by the Purchasing Officer and/or the Board.  Requests for withdrawal are usually denied, unless the bidder proves to the satisfaction of the Purchasing Officer and/or the Board that the mistake was either a scrivener's error or another type of clearly unintentional error so departing from customary and reasonable business practices as to be obvious and to legitimately and substantially impair the vendor's business.

 

6.            INSPECTION OF SITE

Each bidder shall visit the site and become informed fully as to the condition under which the work is to be done.  All visitors must report to and register in the main office.  Failure to do so will not relieve a successful bidder of his/her obligation to finish all material and labor necessary to carry out the provisions of the contract documents at the price(s) bid.

 

Where the specifications require field measurement the bidder shall perform the measurement and the Board assumes no responsibility for error in measurement.  The bidder shall be expected to provide the item or material specified and to make good any situations which arise from error in measurement.

 

Site visits shall not be made after regular working hours, on Sundays, school holidays, or legal holidays, unless previously agreed to by the Purchasing Department.

 

7.            QUOTATION

The bidder shall complete the information requested on the proposal form(s).  Prices quoted shall not exceed the prices established under any governmental price control regulations.

 

All prices shall be firm for a period of ninety (90) days from the date of bid opening unless otherwise stated under Special Notices.  This applies to all vendors, whether they have received an award or not.  THE BOARD RETAINS THE RIGHT, WITH MUTUAL CONSENT OF THE BIDDER(S), TO UTILIZE BID PRICING WITH APPROVED PRICE CHANGES FOR FUTURE PURCHASES FOR AS LONG AS THE BIDDER(S) AGREES TO EXTEND THE CONTRACT.

 

The Board will not accept any proposal with escalator clauses, minimum order requirements or irregular features unless specifically authorized under "Special Notices".  No charge will be allowed for cases, boxes, cardboard, bottles, etc., or for freight expenses.  Charges for express delivery will only be allowed if requested by the Board.  Empty packages, cases, boxes, cardboard, bottles, etc., must be removed by the contractor at his/her own expense.

 

If the contract includes equipment, all prices must be FOB-Destination (inside delivery).  The bidder(s) is encouraged to bid only one product per line item that most nearly meets the specifications.  If the bidder believes that there are more than one product available, a limit of two (2) offers will be considered for each line item.

 

If two or more particular brands, models, or makes are listed in the specification (under Base and Alternate bids) and the bidder has not indicated in the bid which of the two or more brands, models, etc., is being bid, it shall be understood that the Board may require the contractor to furnish whichever is preferred by the Board.

 

8.            DISCOUNTS

The Board reserves the right to consider discounts in evaluating the bid.  All discounts other than prompt payment should be calculated by the bidder.

 

9.            BIDS FOR ALL OR PART

A bidder may restrict his/her bid to be considered in the aggregate by so stating, but should name a unit price on each item bid upon.  Any bid in which the bidder names a total price for all the items, without quoting a price on each and every separate item, may be considered non-responsive.  Unless a bidder has restricted his/her bid, award may be made to the bidder submitting the lowest aggregate bid on a group of items of a similar nature or on an individual item basis, or any other basis deemed to be in the best interest of the Board.

 

10.          STANDARD OF QUALITY, "OR EQUAL CLAUSES", MATERIALS SUBSTITUTIONS

Unless otherwise specified, all materials used for the manufacture or construction of any work covered by this bid shall be new and the workmanship shall be of the highest quality.  Any material or article which will perform adequately the duties imposed by the general design will be considered equal and satisfactory. This is providing the material or article so proposed is of equal substance or function in the Purchasing Officer's opinion.

 

THE BRAND SPECIFIED IS USED ONLY TO ESTABLISH A QUALITY LEVEL.  EQUIVALENT ITEMS WILL BE ACCEPTED UNLESS SPECIFICALLY NOTED OTHERWISE IN SPECIAL NOTICES.

 

When permitted in the specifications, bidders on construction contracts only may propose substitute items in their bid proposal, listing the manufacturer, brand name, model number, and nomenclature with reference to the page and paragraph in the specification where the substitution applies.  There proposed substitutions do not need approval prior to submission of bid proposals unless required in the specifications.  The substitutes must be approved by the Board before the contract award.  Proposals of substitutes not acceptable to the Board can result in rejection of the bid or non-award of the contract.

 

In the absence of any statement to the contrary by the bidder, the bid will be interpreted as being for the exact brand and/or qualities, etc., enumerated in the detailed specifications, whenever the specifications indicate a product of a particular manufacturer, model or brand.

 

If for any reason the contractor cannot guarantee his/her work using a material or equipment which has been specified, he/she shall so notify the Board in writing at least seven (7) days in advance of the bid opening, giving reasons, together with the name and data concerning substitute products proposed.  Requests for substitutions must be accompanied by documentary proof of equality and delivery from suppliers of both specified and proposed equipment or materials.  A statement of any credit or extra cost involved shall also be included with the request.

 

Request for approval of substitutions may not be considered a cause for delay in any phase of the work to be accomplished. The Board's decision will be the final authority in all cases.

 

11.          SAMPLES

Samples may be requested by the Purchasing Department for testing and evaluation purposes.  Failure to submit samples as required at the time designated by the Purchasing Department shall be cause for rejection of that item.

 

 

All samples must be delivered with all charges prepaid to the FREDERICK COUNTY PUBLIC SCHOOLS, Hayward Complex, Purchasing Department, 33 Thomas Johnson Drive, Frederick, Maryland  21702, plainly marked to indicate make/model, item #, name of bidder, bid name and number, date of bid opening, and must be accompanied by instructions as to the return thereof.

 

Accepted samples may be retained during the life of the contract.  The right is reserved to retain any sample submitted with bids whenever deemed necessary to do so for the purposes of examination and testing.  The Board reserves the right to use all samples in any manner which may best serve the final determination of the successful bidder, even if said examination and testing results in damage to or destruction of the sample.

 

Samples that are not retained shall be removed by the vendor within two weeks upon notification of the Award/Non-Award letter by the Board.  Unless the samples, when received by the Purchasing Department, are accompanied with instructions as to their return, and include sufficient funds to defray shipping charges or provide for return by freight or express on a collect basis, samples shall become the property of the Board.  Samples not removed within this two week period shall be disposed at the discretion of the Purchasing Department.  Disposal may include retention and use by the Board without compensation to the bidder or person furnishing the samples.

 

12.          BID BOND

Bid bonds are not required at this time except under special circumstances.  See the Special Notices section of the bid document, if applicable.

 

13.          PERFORMANCE AND PAYMENT BONDS

Performance and payment bonds are not required on all bids.  See the Special Notices section of the bid document, if applicable.  If applicable, the successful bidder(s) may be required to submit either one or both of the following two (2) bonds to the Purchasing Department within ten (10) calendar days of receipt of the Notice of Award and in accordance with the terms stated below:

 

A.           Performance Bond in the amount of 100% of the contract price covering faithful performance of the contract; and

 

B.            Payment Bond in the amount of 100% of the contract price as security for the payment of all persons performing labor and furnishing materials in connection therewith.

 

The cost of the performance bond and payment bond will be borne by the bidder(s) in all instances.

 

Certified checks in the amounts stated above will be accepted in lieu of the performance bond and payment bond only prior to approval of the Purchasing Officer.  If checks are approved for acceptance in lieu of either bond, they should be in the same amount as these bonds;  be separate checks;  and should clearly designate the purpose -i.e., performance or payment.

 

Certified checks, if submitted, will be deposited in the Board's bank account(s).  Upon successful completion of the contract, check(s) will be drawn upon the Board's bank account(s) for the full amounts of both certified checks.

 

Bonds must be approved by surety companies which are named in the most current Circular 570 "Surety Companies Acceptable on Federal Bonds" as issued by the U.S. Treasury, Bureau of Government Finance Operations, Division of Banking and Cash Management, Washington, D.C.  20111.  Bonding companies shall be rated A - or above by A.M. Best Company.

 

If a bonding company is used that is not on the most current Circular 570, the vendor will be contacted to obtain a bond from an approved surety company and resubmit it to the Purchasing Department within ten (10) working days after contact.

 

Upon receipt and approval of the performance bond and payment bond or the certified checks, an official purchase order will be issued and the contract initiated.

 

 

 

14.          CONTRACTOR'S AND SUBCONTRACTOR'S INSURANCE

See the Special Notices section of the bid document for any changes to the insurance requirements, if applicable.

 

The Owner is to receive insurance certificates evidencing the compliance of insurance requirements at least ten (10) days before Work commences.  The contractor shall not commence work until such insurance has been approved by the Board, nor shall the contractor allow any subcontractor to commence work on his/her subcontract until the insurance required of the subcontractor has been obtained and approved.

 

A.           WORKER'S COMPENSATION & EMPLOYERS' LIABILITY INSURANCE

The contractor shall procure and shall maintain during the life of the contract Worker's Compensation Insurance as required by applicable State law for all of his/her employees to be engaged in work at the site of the project under the contract and, in case of any such work sublet, the contractor shall require the subcontractor similarly to provide Worker's Compensation Insurance for all of the latter's employees to be engaged in such work unless such employees are covered by the protection afforded by the contractors Worker's Compensation Insurance.

 

In addition, the contractor shall procure and shall maintain during the life of the contract Employers' Liability Insurance in the following amounts:

 

E.L. Each Accident                $100,000.00

E.L. Disease - Each Employee              $100,000.00

E.L. Disease - Policy Limit                    $500,000.00

 

The contractor will require any subcontractor to procure and maintain Worker's Compensation and Employer's Liability Insurance during the life of the contract.  It will be the responsibility of the contractor to ensure that all subcontractors comply with this provision, and the contractor will indemnify and hold harmless the Board for the failure of the contractor or any subcontractor to comply with these provisions.

 

B.            COMMERCIAL GENERAL LIABILITY INSURANCE

The contractor shall procure and shall maintain during the life of the contract Commercial General Liability Insurance including premises and operations, completed operations and products, on a per occurrence basis, with at least the following limits:

 

General Aggregate                                               $2,000,000 per project

 

Products-Completed Operations Aggregate                        $2,000,000                 

 

Personal & Advertising Injury                                             $1,000,000

 

Each Occurrence                                                                $1,000,000

 

Fire Damage                                                                       $   50,000

 


Medical Expense                                                                $    5,000

 

The XCU Coverage for explosion, collapse, and underground property damage shall not be excluded from the policy.

 

Completed operations liability coverage shall be in force for one year after completion of work.

 

C.           COMPREHENSIVE AUTOMOBILE LIABILITY                                                                      

The contractor shall maintain Comprehensive Automobile Liability Insurance (including all automotive equipment owned, non-owned and hired, operated, rented, or leased).  Minimum limits of Automobile Liability Insurance shall be:

 

Bodily Injury                                                                       $1,000,000 per person/$1,000,000 accident

 

Property Damage                                                               $1,000,000 each occurrence, or

 

Combined Single Limit Bodily Injury

and Property Damage Liability                                            $1,000,000

 

D.           SCOPE OF INSURANCE AND SPECIAL HAZARDS

The insurance required in B. and C. above shall provide adequate protection for the contractor and subcontractors, respectively, against damage claims which may arise from operations under the contract, whether such operations be by the insured or by anyone directly or indirectly employed by him/her and, also against any of the special hazards which may be encountered in the performance of this contract as enumerated in B. above.  Insurance coverage required under B. above shall specifically include property damage caused by conditions otherwise subject to exclusions"X,C,U" (Explosion, Collapse or Underground Damage) as defined by the National Bureau of Casualty Underwriters.  Exceptions: contracts that do not require excavation or underground work are not required to have the above "X,C,and U" coverage.

 

E.            SUBCONTRACTOR'S INSURANCE

The contractor shall either

(1)  require each of his/her sub-contractors to procure and to maintain during the life of          the subcontract Liability Insurance of the type and in the same amounts as

      specified in D. above, or

(2) insure the activities of the subcontractors in his/her own policies.  It will be the

     responsibility of the contractor to insure that all subcontractors comply with this

     provision, and the contractor will indemnify and hold harmless the Board for the

     failure of any subcontractor to comply with this provision.

 

F.            BUILDER'S INSURANCE

The Contractor shall provide and maintain Builder's Risk Protection in the name of the Owner,  Board of Education of Frederick County, the Frederick County Board of Commissioners and the general contractor. The policy shall stipulate coverage for Full Value of the Work on a Replacement Cost Basis and that losses are payable directly to the Owner.  The policy shall provide coverage for perils of fire and extended coverage, theft, vandalism, malicious mischief, collapse, false work, temporary structures, demolition, debris removal, flooding and other such insurance coverage as required by the Contract Documents.  These policies shall remain in effect until completion of punch list items.

 

This provision shall not release the contractor of the obligation to complete according to plans and specifications the project covered by the contract, and the contractor and his/her Surety shall be obligated to full performance of the contractor's undertaking. 

 

G.           PROOF OF CARRIAGE OF INSURANCE

The contractor shall furnish the Board with certificates showing the type, amount, class of operations covered, effective dates and dates of expiration of policies.  Such certificates also shall contain substantially the following statement:  "The insurance covered by this certificate will not be cancelled or materially altered, except after thirty (30) days written notice has been received by the Board."

 

H.           The Owner,  Board of Education of Frederick County, the Frederick County Board of Commissioners and other entities stipulated by the Owner, shall be named as additional insureds on all Contractor policies.  The Contractor's insurance shall be primary and non-contributory to any insurance carried by the Board of Education of Frederick County or other entity.  Waiver of subrogation applies to above policies in favor of the certificate holder.  Insurance providers must have an AM Best Company rating of at least A- / XII.

 

15.          AWARDS OR REJECTION OF BIDS

In general, it is the intention of the Board to make awards to bidders submitting the lowest bid prices provided; (a) all the terms of the invitation have been met; (b) the prices are reasonable; and (c) it is in the best interest of the Board to accept them.

 

The Board reserves the right to determine completeness and/or timeliness of bids, to reject any or all bids in whole or in part, to make partial awards, to waive any irregularity in any quotation, to increase or decrease quantities if quantities are listed in the bid, to reject any bid that shows any omissions, alterations of form, additions not called for, conditions, or alternate proposals, and to make any such award as is deemed to be in its best interest.

 

Bidders may be required, before the awarding of a contract, to show to the complete satisfaction of the Board that they have the necessary facilities, ability, and financial resources to execute the work in a satisfactory manner, and within the time specified.  Bidders must demonstrate that they have the necessary experience, history and references which will assure the Board of Education of their qualifications for executing the work.  (A detailed audited financial statement may be required.)

 

Bidders are required, as a part of their bid submission, to provide information regarding their firm’s status as a Minority Business Enterprise (MBE) and the diversity of their firm’s board of directors and company officers.  Bidders also are required, as a part of their bid submission, to provide a plan for the utilization of minority contractors, subcontractors or suppliers in executing the contract, if their firm receives an award.

 

The Board reserves the right to reject the bid of a bidder who has, in the opinion of the Board, previously failed to perform properly in contracts of a similar nature, or the bid of a bidder who investigation shows is not in a position to perform the contract.

 

The Board reserves the right to award the bid within ninety (90) days from the date of the bid opening unless a different time period is stated in the bid document.

 

In the event of tie bids where all other factors such as past performance are considered comparable, the awards shall be made to the Frederick County based vendor; the out-of-county but Maryland based vendor; and the out-of-state based vendor, in that order of preference.

 

16.          OBJECTION TO AWARD RECOMMENDATION

Any bidder objecting to the Purchasing Officer's recommendation for award may protest the Purchasing Officer's action by formally notifying, in writing, the Executive Director of Fiscal Services.  The bidder's written protest must be received in the Purchasing Department at least five (5) days prior to the Board meeting for which the bid award is scheduled.  It is the vendor's responsibility to ascertain the date and time of the pertinent Board meeting.  The protest must specifically and fully identify the bidder's objection(s); the legal basis for the objection, including the itemization of laws, regulations, policies, or bid procedures, etc., which have been allegedly violated; a statement of all facts which support the bidder's position; a copy of all documents which are relevant or upon which the bidder is relying; and a statement as to the relief sought by the bidder.

 

17.          OBJECTION TO AWARD

Any objections to an award made by the Board must be filed, in writing, to the Executive Director of Fiscal Services and received within ten (10) calendar days following the date of the award by the Board.  The objection must specifically and fully identify the vendor's objections and any supporting legal or procedural authority.

 

18.          CONTRACT

When the Board accepts a bid and awards a contract, the purchase order, bidder's submission agreed upon the schedules, addenda, and any agreed upon shop drawings, schedules, and other documents will become a part of the contract.  Notification of the contract award will be made by letter after approval by the Board.

 

19.          SHOP DRAWINGS

The contractor shall verify all field measurements and shall submit three copies of all shop drawings and schedules required for the work of various trades.  The Board shall review these documents only for conformance with the design concept of the project and compliance with the information given in the contract documents.  The contractor shall make any corrections required by the Board, file with them two corrected copies and furnish such other copies as may be needed.  The Board's review of such documents shall not

relieve the contractor of the responsibility for deviations from drawings or specifications, unless he/she has in writing called the Board's attention to such deviations at the time of submission, and secured their written approval.  Nor shall it relieve him from responsibility for errors in these documents.

 

20.          AMERICAN STEEL REQUIREMENT             

The contractor shall comply with the provisions of Sections 17-301 through 17-306 of the State Finance and

Procurement Article of the Annotated Code of Maryland, as amended entitled "Steel Procurement for Public Works."  The contractor's affidavit of compliance with these provisions may be required before payment can be made.

 

21.          SURVEYS, PERMITS, LAWS, REGULATIONS, ROYALTIES, PATENTS AND TAXES

The Board shall furnish all surveys unless otherwise specified.

 

Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.

 

The Contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as drawn and specified.  If the contractor performs any work which it knows or should know to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Board, he/she shall bear all costs arising there from.

 

Wherever the law of the place of building requires a sales, consumer, use, or other similar tax, the contractor shall pay such tax.

 

The contractor shall pay all royalties and license fees.  He/she shall defend all suites or claims for infringement of any patent rights and shall save the Board harmless from loss.

 

No charge will be allowed for Federal excise taxes, from which the Board is exempt.  Exemption certificates, if required, will be furnished on forms provided by the bidder.  Contractors and subcontractors who bid on the construction jobs for the Board after July 1, 1968, should include the MARYLAND SALE AND USE TAX on all purchases.  Contractors will be required to pay the tax on all purchases and can recover it only as a part of their bid price.

 

22.          USE OF PREMISES, PROVISION OF PORTABLE SANITATION AND REMOVAL OF DEBRIS

Contractors are responsible for removal of trash and debris and shall confine their apparatus, materials, supplies, and equipment in such orderly fashion at the work site so that it will not unduly interfere with the progress of the work or any other contractor.

 

Only such loads as are consistent with the safety of that portion of the work shall be placed upon the work or any part thereof.

 

It shall be the contractors' responsibility to provide portable sanitation facilities on the work site and secure Health Department or local subdivision approval, where required.

 

They shall not interfere with Board personnel or students while they are conducting their required business.


The Board reserves first right of salvage on all materials removed from Board facilities and no salvage values should be assumed in bidding on the project unless so stated in the specifications.  Contractors shall pay all disposal fees and can recuperate them only by including them in the price bid.

 

At the completion of the work and before final payment is made, contractors shall remove all rubbish from and about the building, and all tools, scaffolding and surplus materials, and shall leave the work site clean, including proper landscaping.  In case of dispute, the Board may remove the rubbish and charge the cost to the contractor.

 

23.          USE OF MATERIALS, SERVICES AND FACILITIES

It is understood that, except as otherwise specifically stated in the contract documents, the contractor shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, superintendence,

temporary construction and all other services and facilities of every nature whatsoever necessary to execute, complete and deliver the work within the specified time.

 

The sale or use of tobacco products in any form is prohibited in school buildings at all times.  School buildings are defined as a local school system owned or leased building.

 

The sale or use of tobacco products in any form is prohibited on school grounds during the hours of 7:00 a.m. to 5:00 p.m., Monday through Friday and all other times during school sponsored events.  School grounds are defined as local school system owned or leased land that surrounds a school building.

 

The tobacco-free school environment policy states that any person or organization permitted to use school buildings or school grounds (e.g., use of facility form) must comply with the policy.

 

Any work necessary to be performed after regular working hours, on Sundays or legal holidays, shall be performed with the approval of and without additional expense to the Board, unless previously agreed to.

 

24.          CHANGES IN WORK

No changes in the work covered by the approved contract documents shall be made without having prior written approval of the Board.  The contract sum may be adjusted accordingly with the consent of the Surety first being obtained where necessary or desirable.

 

Charges or credits for the work covered by the approved change shall be determined by one or more or a combination of the following methods:

a. Unit bid prices previously approved

b. An agreed lump sum

c. The actual cost of:

1. Labor, including foremen

2. Materials entering permanently into the work

3. The ownership or rental cost of construction

   plant and equipment during the time of use the extra work

4. Power and consumable supplies for operation of power equipment

5. Insurance

6. Social Security, (F.I.C.A.) and unemployment contributions.

 

To the cost under c. there shall be added a fixed fee to be agreed upon

                              but not to exceed fifteen per cent (15%) of the estimated cost of the work.  The fee

                              shall be compensation to cover the cost of supervision, overhead, bond, profit, and any

                              other general expenses.

 

25.          WORK SITE SUPERVISION

At the work site, the contractor shall employ a construction superintendent or foreman who shall have full authority to act for the contractor.  The superintendent shall not be changed except with the consent of the Board.  The superintendent shall represent the contractor in his/her absence and all directions given to him shall be as binding as if given to the contractor.  The Board shall not be responsible for the acts or omissions of the superintendent or his/her assistants.

 


The contractor shall at once report to the Board any error, inconsistency or omission which he may discover, but he/she shall not be liable to the Board for any damage resulting from any errors or deficiencies in the contract documents or other instructions given by the Board.

 

26.          SUBCONTRACTORS

The contractor shall give his/her personal attention constantly to the faithful execution of this contract.  The contractor shall keep the same under his/her own control and shall not assign or sublet by Power of Attorney or otherwise the work or any part thereof without the previous consent of the Purchasing Department.  The contractor may be required to submit to the Purchasing Department, in writing, the name of each subcontractor he/she intends to employ, the portion of the material to be furnished, his/her place of business, and any such information as may be required in order to know whether such subcontractor is reputable and reliable and able to furnish the material as called for in the specifications.

 

The contractor shall not legally or equitably assign any of the funds payable under the contract or its claim thereto, unless by and with the consent of the Purchasing Department.

 

The contractor shall have the same provisions inserted in all subcontracts relative to the terms of the General Conditions and other contract documents.  Nothing contained in this contract shall create any contractual relations between any subcontractor and the Board.

 

The Board reserves the right to approve or disapprove all subcontractors to be employed on a project.  The Board reserves the right to approve or disapprove a change of subcontractor once an initial subcontractor has been approved.  In the event the Board fails to approve a subcontractor or requires a change of subcontractor, the contractor shall be liable for any increase in cost incurred as a result.

 

27.          LOCAL LICENSING OF TRADE PERSONS

All trade persons performing work under this contract as a general contractor or a subcontractor must be licenses in accordance with the requirements of the local subdivision and State, as appropriate.  Any cost incurred as a result of this licensing requirement shall be borne by the contractor.

 

28.          PROTECTION OF WORK AND PROPERTY

The contractor shall at all times safely guard his/her own work, adjacent property, and the Board's property from damage, injury, or loss in connection with this contract.  The contractor shall replace or make good any such damage, loss, or injury at his/her own expense, and at current replacement cost unless such be caused directly by errors contained in the contract or by the Board.

 

In case of inclement weather or an emergency that threatens loss or damage of property or safety of life, the contractor will be allowed to act in a diligent manner, without previous instructions from the Board.  He/she shall notify the Board thereafter of his/her actions.  Any claim for compensation by the contractor due to such extra work shall be promptly submitted to the Board for approval.

 

Where the contractor has not taken action but has notified the Board of an emergency threatening injury to persons or damage to the work or any adjoining property, he/she shall act as instructed or authorized by the Board.

 

The contractor shall take all necessary precautions for the safety of employees on the work site and shall comply with all applicable provisions of Federal, State, and Municipal safety laws and building codes.  He/she shall erect and properly maintain at all times, as required by the conditions and progress of the work, all necessary safeguards for the protection of workers and the public and shall post danger signs warning against the hazard created by such features of construction as protruding nails, hoist, well holes, elevator hatchways, scaffolding, window openings, stairways, and falling materials.  He/she shall designate a responsible member of the organization to be on the work site, whose duty shall be the prevention of accidents.  The name and position of any person so designated shall be reported to the Board by the contractor.

 

29.          HEALTH AND SAFETY STANDARDS

When applicable, all machinery/equipment must meet OSHA-MOSHA requirements as to the safety of the operation of the equipment.  All required safety devices shall be included in the price(s) bid.

 

When applicable, kitchen equipment and supplies must meet Maryland State Health Department, National Sanitation Foundation (NSF) and Frederick County Health Department requirements.

 

All construction activities must be conducted in strict compliance with OSHA/MOSHA requirements.

 

The contractor and subcontractors are required to comply with all provisions of the Access to Information About Hazardous and Toxic Substances Act, a part of the Maryland Occupational Safety and Health Law.

 

30.          ASBESTOS

The contractor is responsible to report to the Board any asbestos material or suspected material found or uncovered that is not part of the scope of the project.  In addition, he/she may not introduce new asbestos or asbestos bearing materials into the site.

 

It is the responsibility of the contractor to comply with all Municipal, State, and Federal EPA regulations and laws when handling or disposing of asbestos materials.

 

If the contractor intentionally endangers or jeopardizes the health of any building/school occupant through mishandling of hazardous material, the contractor will be held liable for such action.

 

 

31.          INSPECTIONS AND CORRECTION OF WORK

All work, all materials, whether incorporated into the work or not, all processes of manufacturer, and all methods of construction shall be at all times and places subject to the inspection of the Board, whose representatives shall be the final judge of the quality and suitability.  Should these fail to meet this approval they shall be forthwith reconstructed, made good, replaced and/or corrected, as the case may be, by the contractor at his/her own expense.  Rejected material shall be removed immediately from the site.  If, in the opinion of the Board, it is undesirable to replace any defective or damaged materials or to reconstruct or correct any portion of the work injured or not performed in accordance with the contract documents, the compensation to be paid to the contractor hereunder shall be reduced by such amount as in the judgment of the Board shall be equitable.

 

The Board's representative shall at all times have access to the work wherever it is in preparation or progress and the contractor shall provide proper facilities for such access.

 

If the specifications, laws, ordinances or any public authority require any work to be specially tested or approved, the contractor shall give the Board timely notice of its readiness for observations.  If the inspection is by another authority, the contractor shall notify the Board of the date fixed for such inspection and shall use the required Certificates of Inspection.

 

If any work should be covered up without approval or consent of the Board, it must, if required, be uncovered for examination at the contractor's expense.  Re-examination of questioned work may be ordered by the Board and, if so ordered, the work must be uncovered by the contractor.  If such work is found to be in accordance with the contract documents, the contractor shall pay such cost.  If the defect in the work was caused by another contractor employed by the Board, the Board shall pay such cost and recover the charges from the other contractor.

 

32.          GUARANTEE

Neither the final certificate of payment nor any provision in the contract documents nor partial or entire occupancy of the premises by the Board shall constitute an acceptance of work not done in accordance with the contract documents or relieve the contractor of liability in respect to any express warranties or responsibility for faulty materials or workmanship.

 

The contractor shall guarantee the material and workmanship on all services, equipment, materials, supplies, and labor furnished by him for a period of one (1) year from the date of acceptance, unless a longer or shorter period of time is stated elsewhere in the specifications.  If, within the guarantee period, any defects or signs of deterioration are noted, the contractor, at his/her expense, shall correct the condition, or he/she shall replace the part or entire unit of work/equipment to the complete satisfaction of the Board.  These repairs, replacements, or adjustments shall be made only at such times as will be designated by the Board as least detrimental to the instructional programs.

 

Should the contractor fail to comply with the terms of this guarantee, the Board may have such work performed as it deems necessary to fulfill the guarantee, charging the cost to the contractor.

 

33.          LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE ON TIME

Failure by the contractor to complete the work of the contract or within the time specified stated on the proposal form will entitle the Board to deduct and retain out of funds which may be due the contractor under this contract, a sum as follows for each calendar day in excess of the time stated, (including Saturday, Sundays, and legal holidays) until the contract is complete in accordance with the specifications.

 

The completion date for construction/renovation contracts is defined as substantial completion with a Use and Occupancy permit (if applicable).  Liquidated damages will be assessed at the following rates:

 

 

Amount of Contract                              Liquidated Damages              Liquidated Damages

(per calendar day)  Beyond 21 days

(per calendar day) 

$200,000 or less                                  $350                                     $700

$200,000 to $1,000,000                      $500                                     $1,000

 

(This document will not be used for contracts exceeding $1,000,000.00)

 

This sum shall not be considered as a penalty but as a sum mutually agreed upon as the damages suffered by the Board because of delay.

 

Requests for extension of completion time due to strikes, lack of materials or any other causes over which the contractor has no control will be reviewed after written applications is made to the Purchasing Department. Requests must occur immediately upon occurrence of conditions for a time extension.

 

34.          BILLING AND PAYMENT

The contractor shall furnish satisfactory bills, payrolls and vouchers covering all items of cost.  When requested, they shall give representatives of the Board access to accounts relating thereto.

 

Partial payments may be made at specific intervals depending upon the length and dollar value of the project. When partial payments are requested, the invoice or requisition for payment should be sent to the Finance Department for payment.  Invoices for partial payments should show only the work performed and/or materials/equipment supplied and on site.

 

An amount of 10% from each application for payment will be withheld until final acceptance of the project by the Board.  This amount may cover possible unsatisfactory performance or other damages.

 

Invoices shall be submitted in triplicate to:

FREDERICK COUNTY PUBLIC SCHOOLS

Hayward Complex

Finance Department

7630 Hayward Road

Frederick, MD 21702

Attn: Accounts Payable Dept.

 

Invoices must be submitted in the same format as the proposal form or purchase order.

 

Invoices and packing slips must contain the following information:

-  Bid Number

-  Purchase Order Number

-  Item Number (if applicable)

-  Quantity (if applicable)

-  Brief Description of Item or Work Performed

-  Unit Price Bid/Partial Payment Amount

-  Extended Total for Each Item

-  Grand Total

-  Public School Construction Number (PSC) (if applicable)

 

35.          RESERVATIONS AND ANNULMENTS

The Board reserves the right to void, cancel, annul any contract if, in its opinion, there shall be a failure, at any time, to perform faithfully any of its stipulations, or in case of any willful attempt to impose upon the Board materials, products and/or workmanship inferior to that required by the contract.  Any action taken in pursuance of this latter stipulation shall not affect or impair any rights or claims of the Board to damages for the breach of any covenant of the contract.

 

Should the contractor fail to comply with the conditions of this contract or fail to complete the required work within the time stipulated in the contract, the Board reserves the right to purchase on the open market, or to complete the required work, at the expense of the contractor, or by recourse to provisions of the performance bond if such bond is required under the conditions of this bid.  The Board also reserves the right to withdraw such items or required work from the contract and subtract associated costs from the contractor's contract price

without incurring further liabilities on the part of the Board.  The contractor and his/her Surety shall be liable to the Board for any excess cost incurred by the Board in such an event.  The Board may take possession of and utilize, in completing the work, such materials, appliances, and plant as may be on the site of the work and necessary for its completion.

 

The Board places all contractors and vendors on notice that an Assurance of Compliance with the Civil Rights Act of 1964 has been signed by the Superintendent of Schools as authorized by the Board.

 

36.          NO PREVAILING WAGE RATES

However, when applicable (see "Special Notices"), the contractor shall comply with Section 17-201 through 17-226 of the State Finance and Procurement Article of the Annotated Code of Maryland, as amended, which requires payment of prevailing wages as determined by the Commissioner of Labor on public works projects.

 

37.          HOLD HARMLESS

It is understood that firms providing quotes for this project shall defend and hold harmless the Board of Education of Frederick County and its representations from all suits, actions, or claims of any kind brought about as a result of any injuries or damages sustained by person(s) or property during the performance of this contract.

 

38.          PUBLIC INFORMATION ACT NOTICE

Vendors should give specific attention to the identification of those portions of their bids which they deem to be confidential, or to contain proprietary information or trade secrets.  Vendors should provide justification why such material, upon request, should not be disclosed by the School System under the Maryland Public Information Act, State Government Article, Section 10-611 through 628, Annotated Code of Maryland.

 

39.          CONTRACT DISPUTE

        Any dispute resulting from a question or fact arising under this contract shall be decided by the Frederick County Public Schools’ contract administrator and the purchasing officer who will reduce their decision to writing and furnish a copy thereof to the Contractor.  This decision shall be final and conclusive unless within thirty (30) days the Contractor furnishes to the contract administrator and purchasing officer a written appeal addressed to the Board of Education (BOE) of Frederick County.  The local Board of Education has the right to hear appeals as provided by Maryland law.

              

               The Board of Education or duly authorized representative will review the appeal for the determination of such appeal and their finding shall be final and conclusive.  Exceptions are decisions determined by a court of competent jurisdiction to have been fraudulent, capricious, arbitrary, or so grossly erroneous as to imply bad faith, or not supported by evidence.  In connection with any appeal proceeding under this clause the Contractor will be afforded an opportunity to be heard and to offer evidence in support of his appeal.  Pending final decision of a dispute, the Contractor shall proceed diligently with the performance of the contract and in strict accordance with the FCPS staff’s decision.

              

        This clause does not preclude consideration of laws questioned in connection with the decision provided for above.

 

 

 

Revised: February 3, 2003